timeline

Author an interactive project timeline entirely in Markdown. A fenced ```timeline block written in YAML declares a chain of named, offset dates — calendar days or business days, with optional holiday/blackout exclusions — and renders as a date picker per anchor date plus a Mermaid gantt diagram that recomputes live as you change a date. Like calculator, all of the math happens client-side — no server, no rebuild.

It is a first-party Netdocs plugin (there is no MkDocs equivalent). Enable it in plugins:

appsettings.json
{ "name": "timeline" }

Example

```timeline
title: Communications
date_format: MM/DD/YYYY
show_summary: true
display_date_format: "dddd MMM dd, yyyy"
edit_exclusions: true
inputs:
  - name: start
    label: Project Start
    default: 01/01/2027
outputs:
  - name: first
    label: Project Announcement Email
    type: all
    expr: start
    duration: 1
  - name: second
    label: Kick Off Meeting
    type: weekdays
    expr: first + 1
    duration: 1
  - name: sprint1
    label: Sprint 1
    type: weekdays
    expr: second + 1
    duration: 10
  - name: sprint2
    label: Sprint 2
    type: weekdays
    expr: sprint1 + 1
    duration: 10
  - name: projectclosure
    label: Project Closure Meeting
    type: weekdays
    expr: sprint2 + 1
    duration: 1
```

Renders as:

Communications

Change the Project Start picker above — the whole chain redraws immediately: each sprint's bar starts the weekday after the previous one ends, not the day it started. Since edit_exclusions is on, try adding a holiday in the middle of Sprint 1 too — its end date (and everything after it) shifts to absorb the extra day.

How it works

The plugin runs as a Markdown preprocessor (order 15, same tier as calculator) and rewrites each timeline fence into raw HTML: one <input type="date"> per inputs[] entry, an empty container for the diagram, and a JSON "spec" of the whole output graph (names, labels, types, and each expr already parsed into a {ref, direction, count} triple). None of that changes after the page builds.

A site-wide script (registered once, not per-diagram) reads that spec, and on page load and every time an input changes: re-derives every output date from the current input values (in declaration order — an expr may only reference a name defined earlier in the same block), rebuilds the mermaid source text, and renders it via a lazily-imported Mermaid straight into the page — no server round-trip. Date arithmetic runs on a plain day-count algorithm rather than JavaScript's Date, which sidesteps that type's timezone-shift quirks entirely.

Every milestone gets a real slot on the date axis (dateFormat/axisFormat); the generated source also sizes the font and picks a tickInterval from the actual date span so a short project doesn't get padded out to an unreadably wide axis.

Inputs

Every field below is a direct top-level key — title, date_format, exclusions, show_summary, display_date_format, edit_exclusions, inputs, outputs are all siblings. There's no nested settings object to learn as a second rule.

Field Type Default Required Description
title string no Diagram title and section name.
date_format string MM/DD/YYYY no Token format for every date authored in this block (default, exclusions).
exclusions array no Dates that never count as a landing day — see Exclusions.
show_summary boolean true no Show the exact-date table below the diagram, sorted chronologically regardless of declaration order (the diagram's own row order stays grouped by input/output as declared).
display_date_format string dddd MMM dd, yyyy no How dates are displayed in that table and the exclusions list — see Display date format.
edit_exclusions boolean false no Let the reader add/remove excluded dates in the page itself — see Editing exclusions.
inputs array yes The anchor date(s) everything else is computed from.
outputs array yes Named, computed dates.

inputs[]

Field Type Required Description
name string yes Reference name used in outputs[].expr. Must be a valid identifier ([A-Za-z_][A-Za-z0-9_]*).
label string no Milestone/bar label (defaults to name).
default string yes Initial value of the date picker, parsed with date_format.
type string no all (default) or weekdays — which days count while stepping through duration.
duration integer no Whole days, default 0 — see Duration and end dates.
editable boolean no Default true — a date picker the reader can change. false renders default as plain text instead (formatted with display_date_format, not a native picker's browser-locale format) — still a full graph root: duration and outputs[].expr both still work, it just can't be moved in the page.

outputs[]

Field Type Required Description
name string yes Reference name, usable by later outputs. Must be a valid identifier and unique across the block.
label string no Milestone/bar label (defaults to name).
type string no all (default, every calendar day counts) or weekdays (Saturday/Sunday are skipped). Governs both the expr offset and duration.
expr string yes <ref>, <ref> + N, or <ref> - N — see Expressions.
duration integer no Whole days, default 0 — see Duration and end dates.

Expressions

An expr is a reference to an earlier inputs/outputs name, optionally offset by a whole number of days:

expr: start          # same date as start
expr: start + 5
expr: renewal - 10

The offset is counted in whatever unit that output's own type declares — all steps every calendar day; weekdays steps only Monday–Friday. An expr that references an unknown name, or one declared later in the same block, is dropped with a build warning rather than failing the whole page.

Offsets are capped at 100000 steps

That is roughly 274 years, so no real schedule reaches it. The evaluator stops stepping there, and an offset beyond it would silently resolve to whatever date the evaluator had reached — so it is reported as a build warning and the output is dropped, rather than published as a date that looks right and isn't.

Diagram size

The gantt is drawn at the width of the block it sits in, so its labels render at their intended size rather than being scaled down to fit. It is never drawn narrower than 720px, though: below that a gantt starts overlapping its own task names and axis ticks. On a narrow screen the diagram keeps its readable size and scrolls horizontally instead, and the exact-date table underneath stays fully readable either way. Resizing the window redraws it at the new width.

Duration and end dates

Every input and output has a duration (whole days, default 0), stepped the same way an expr offset is — honouring that item's own type and any exclusions. That produces two dates per item: a start (from default, the date picker, or an expr) and an end (start stepped forward by duration).

duration: 0 renders as a milestone — a single point on the axis. A nonzero duration renders as a task bar spanning start to end.

When an expr references an earlier name, it chains off that name's end, not its start — "the next thing begins when this one finishes," not when it started:

- name: sprint1
  duration: 10
  expr: kickoff + 1   # starts the weekday after kickoff *ends*

If kickoff has duration: 0 (a milestone), its start and end are the same date, so this behaves exactly like before duration existed. It only changes behavior once something upstream actually has a span to finish.

Exclusions

exclusions lists dates that are never counted as a landing day, regardless of an output's type — the natural place for holidays or office closures. Every date here — a bare scalar or either side of a { from, to } range — is parsed with the same top-level date_format as inputs[].default; there's one shared format for every date authored in the block, not a separate one per section:

exclusions:
  - 12/25/2027
  - { from: 12/24/2027, to: 12/26/2027 }   # inclusive range

A weekdays output skips weekends and exclusions; an all output skips only exclusions. Concretely, expr: start + 1 with type: weekdays means "the next weekday that isn't an exclusion" — if that lands on a holiday, it keeps stepping forward (or backward, for - N) until it finds one that isn't.

Exclusion ranges are capped

A { from, to } range is expanded eagerly and capped at 366 days; a longer range logs a warning and is truncated.

Display date format

display_date_format is display-only and unrelated to the top-level date_format (which parses dates authored in the YAML) — two fields, one job each, distinct names on purpose so neither can be mistaken for the other. It controls how dates render in the summary table and the exclusions list, using the same tokens as .NET's custom date format strings — d/dd for day-of-month, ddd/dddd for weekday name, M/MM/MMM/MMMM for month, yy/yyyy for year (repeat count controls padding vs. name):

display_date_format 2027-01-06 renders as
dddd MMM dd, yyyy (default) Wednesday Jan 06, 2027
MM/dd/yyyy 01/06/2027
MMMM d, yyyy January 6, 2027
yyyy-MM-dd 2027-01-06

Editing exclusions

With edit_exclusions: true, the excluded-dates list (shown under the inputs, above the diagram) becomes interactive — each date gets a to remove it, and a date picker lets the reader add new ones. Both take effect immediately, exactly like changing an input: everything downstream that steps through the affected type: weekdays (or matches the added/removed exclusion) recomputes.

Communications